Maintaining a comfortable campus
Several primary heating and cooling units are more than 25 years old. The October 26, 2026 campus evaluation updated the condition of seven units and assembled a 13-unit photo inventory to guide phased replacement.

First-phase replacements
| Priority / equipment | Area served | Planning allowance |
|---|---|---|
| 1 — Unit 2 | Worship Center (25-ton system) | $52,000–$71,000 |
| 2 — Unit 4 | West hallway, kitchen and offices (17.5 tons) | $68,000–$85,000 |
| 3 — Unit 6 | Worship Center (25-ton system) | $56,000–$77,000 |
| Combined planning range | Three condition-priority systems | $176,000–$233,000 |
These ranges are turnkey installed planning allowances, not contractor bids. They should not be added to the campaign goal as a separate project. Scopes, controls, rigging, ductwork and final engineering still require confirmation.
All 13 campus HVAC systems
Actual equipment photographs from the October 2026 assessment. Select the most urgent systems based on condition and available funds.

Lobby, offices and restrooms
$40,000–$58,000
Maintain / defer
Working correctly; no repairs needed on October 26.

Worship Center
$52,000–$71,000
Replace first
C1 out of refrigerant; C3–C4 shut off shortly after starting. Two unsuccessful leak repairs.

Worship Center / stage
$42,000–$58,000
Monitor / capital plan
C2 slightly low; recheck during summer peak load.

West hallway, kitchen and rooms
$68,000–$85,000
Replace second
C1 empty from an irreparable leak; duct transition also deteriorating.

Green Room and office
$10,000–$18,000
Maintain
No new October inspection findings.

Worship Center
$56,000–$77,000
Replace third
C1 and C2 require recurrent charging; cooling adequately at inspection.

Kids K8–K9 / hallway
$32,000–$49,000
Recheck
Possible low charge; currently cooling adequately.

Kids K4–K7
$30,000–$42,000
Recheck
Low charge reported; cooling adequately; recheck in warm weather.

Kids lobby / K1–K3
$48,000–$75,000
Maintain
No new October inspection findings.

Kids warming kitchen
$7,000–$13,000
Maintain
No new October inspection findings.

Kids offices
$9,000–$16,000
Maintain
No new October inspection findings.

Kids Venue
$75,000–$115,000
Maintain
No new October inspection findings.

Annex classroom / restroom
$7,000–$13,000
Maintain
No new October inspection findings.
Why we are taking a phased approach
- Protect worship services, children’s ministry and weekday gatherings from unexpected equipment failures.
- Plan replacements thoughtfully rather than relying on emergency repairs to aging systems.
- Improve long-term reliability, energy efficiency and comfort.
- Maintain and monitor equipment that is still operating acceptably.
Sources: Community Church 13 Unit HVAC Photos and Replacement Costs (October 26, 2026); Forward With God Elder Summary (November 8, 2026). Images show actual existing equipment.